Project Schedule
Smithville ISD 2016 Bond Program
Athletic Complex
Project Kick-off
January 2017
Schematic Design
January 2017 - July 2017
Design Developments
April 2017 - September 2017
Contract Documents
August 2017 - September 2017
Bidding / Permitting
September 2017 - October 2017
Construction
November 2017 - July 2018
Junior High Campus
Project Kick-off
January 2017
Schematic Design
July 2017 - September 2017
Design Development
August 2017 - October 2017
Contract Documents
October 2017 - February 2018
Bidding / Permitting
March 2018 - April 2018
Construction
April 2018 - July 2019
Main Campus Renovations
Project Kick-off
May 2018
Schematic Design
May 2018 - June 2018
Design Development
July 2018 - August 2018
Contract Documents
September 2018 - October 2018
Bidding / Permitting
November 2018 - December 2018
Construction
January 2019 - August 2019